CONSTRUCTION UPDATE JUNE 2024

24 Jul

Here is the latest update from The Pt Chevalier to Westmere Improvements Project Team. 

The below link includes all the work being carried out on Point Chev Road and Meola Road.

We'd like to draw your attention to works being carried out on Meola Road that will affect the main club carpark.

The following schedule of night works will be starting on the 28th July.

  • This work is to complete the final layer of asphalt and add the line marking to Meola Rd.
  • This work will take place between 7pm-5am.
  • There are two areas noted below. 
  • Alternate route is to follow the current detour or to use the Motions Rd carpark.

Where
Meola Road [North | South]- Sunday 28th July – Monday 29th July
From Walford Road intersection to the Meola dog park crossing.
Southern side
Meola Road [East]- Tuesday 30th July
From the Scout Den intersection crossing to 3 Meola Road

Click here for the full update